In the Sunzha District, construction continues on the Assin water intake facility, which will have a capacity of 100,000 cubic meters per day.
The project is being implemented as part of the "Infrastructure for Life" national project and will provide high-quality drinking water to approximately 300,000 residents of Karabulak, as well as the Sunzha and Malgobek districts.
At the site, crews are installing infiltration gallery units beneath the riverbed, setting up a storage reservoir, and laying high-strength cast-iron main pipelines.
The project currently involves 43 specialists and 10 units of specialized machinery. The value of the work completed to date exceeds 245 million rubles.