Construction of a new 250-seat school is underway in the Nesterovskoye rural settlement.
Construction is taking place on the site of the former building. To date, the project is 17% complete. The total area of the facility will exceed 5,200 square meters.
Demolition and major earthworks, as well as the installation of the monolithic foundation slab and basement walls, have been completed at the site. Waterproofing of the exterior walls of the underground section is 91% complete. Work on load-bearing structures is also ongoing: shear walls are 47% complete, and the concreting of columns and floor slabs for the lower levels is 45% complete.
The new school will upgrade the rural settlement's educational infrastructure and create more comfortable learning conditions for children. Construction is scheduled to be completed in October 2028.